The development of the mine has evolved from feasibility to production in under 12 months.

The operation commenced at the beginning of September 2002 with construction of the wash plant which was followed shortly thereafter with the commencement of mining.

The company has a fleet of mining equipment including three (3) 50 tonne Cat 773 Haul Trucks, two (2) Cat 988B Wheeled Loaders, a Cat D8 Dozer, and a Grader that is used in the open pit operation.  

 
Over 1000 meters of strike length has been developed and is ready for mining.

 

 